Suspensions and Portable Locations

Suspensions

The Environment Act (Section 18) provides that, where extraordinary circumstances warrant, a licence may be suspended or varied for a period not exceeding 14 days. The Act requires that the suspension or variation be recorded in the public registry. The letter authorizing the suspension will be placed in the appropriate public registry file and recent suspensions are summarized on this page.

The following licence suspensions were approved in the past 60 days

September 24, 2016September 24, 2017

Licencee

Development Type

File No.

Licence No.

Suspension description

Suspension in effect from

Suspension in effect until

Seymourville Community Council Wastewater Treatment Lagoon 2649.10 2714 Discharge of effluent not meeting total coliform limit October 4, 2017 October 14, 2017
Sunnyside Colony Ltd. Wastewater Treatment Lagoon 1172.20 2383 R Discharge of effluent not meeting total coliform limit October 4, 2017 October 17, 2017
Blue Water Lands Ltd. Wastewater Treatment Lagoon 2516.10 1140 Discharge of effluent not meeting total coliform limit September 27, 2017 October 10, 2017
Municipality of Bifrost-Riverton - Riverton Lagoon Wastewater Treatment Lagoon 5475.00 2942 Discharge of effluent not meeting total coliform limit September 28, 2017 October 9, 2017
Rural Municipality of Hanover - New Bothwell Lagoon Wastewater Treatment Lagoon 3366.10 1524 R Discharge of effluent not meeting total coliform limit September 26, 2017 October 11, 2017
Manitoba Sustainable Development - Nopiming Provincial Park Lagoon Wastewater Treatment Lagoon 4033.00 2097 Discharge of effluent not meeting total coliform limit September 27, 2017 October 10, 2017
Shady Lane Holding Co. Ltd. Wastewater Treatment Lagoon 2731.20 2724 R Discharge of effluent not meeting total coliform limit September 25, 2017 October 8, 2017
Netley Colony Ltd. Wastewater Treatment Lagoon 4004.00 2164 Discharge of effluent not meeting total coliform limit September 22, 2017 September 30, 2017
Rural Municipality of West Interlake Wastewater Treatment Lagoon 114.20 1136 R Discharge of effluent not meeting total coliform limit September 15, 2017 September 28, 2017
Rural Municipality of Grahamdale Wastewater Treatment Lagoon 3740.00 1923 Discharge of effluent not meeting total coliform limit September 6, 2017September 24, 2017
Town of Niverville Wastewater Treatment Lagoon 5124.00 2712 Discharge of effluent not meeting total coliform limit September 6, 2017 September 20, 2017
Rural Municipality of St. Frances Xavier Wastewater Treatment Lagoon 3369.202661 R Discharge of effluent not meeting total coliform limit August 21, 2017 August 25, 2017
Rural Municipality of Hanover - Kleefeld LagoonWastewater Treatment Lagoon 1727.201985 R Discharge of effluent not meeting total coliform limitAugust 22, 2017 September 5, 2017 
Rural Municipality of Hanover - Grunthal LagoonWastewater Treatment Lagoon 935.202984 Discharge of effluent not meeting total coliform limit August 22, 2017 September 5, 2017 
Town of Powerview-Pine Falls - Ward One Lagoon Wastewater Treatment Lagoon 3151.10 1386 R Discharge of effluent not meeting total coliform limit August 17, 2017 August 30, 2017
Town of Powerview-Pine Falls Powerview-Pine Falls Wastewater Treatment Lagoon 78.10 638 R Discharge of effluent not meeting total coliform limit August 17, 2017 August 30, 2017
Rural Municipality of Thompson Wastewater Treatment Lagoon 98.10 2099 Discharge of effluent not meeting total coliform limit August 10, 2017 August 23, 2017
Rural Municipality of Rockwood Wastewater Treatment Lagoon 4627.10 2523RR Discharge of effluent not meeting total coliform limit July 28, 2017 August 8, 2017
Rural Municipality of Grey Wastewater Treatment Lagoon 1903 2420 Discharge of effluent not meeting total coliform limit July 28, 2017 August 10, 2017
Rural Municipality of Pipestone Wastewater Treatment Lagoon 89.00 2564 Discharge of effluent not meeting total coliform limit August 9, 2017 August 21, 2017
Rural Municipality of Alexander Wastewater Treatment Lagoon 4747 2304R Discharge of effluent not meeting total coliform limit July 27, 2017 August 9, 2017
Circle Square Ranch Wastewater Treatment Lagoon 2910.10 1365 Discharge of effluent not meeting total coliform limit July 31, 2017 August 13, 2017
Rural Municipality of Grey Wastewater Treatment Lagoon 5418.00 2917 Discharge of effluent not meeting total coliform limit July 31, 2017 August 13, 2017
Town of Powerview-Pine Falls Wastewater Treatment Lagoon 78.10 638 R Discharge of effluent not meeting total coliform limit July 19, 2017 August 2, 2017

For more information, please contact the project contact or the Licensing Clerk.

Portable Asphalt Plant Locations

Company

Env. Licence No.

Location

Operating Period

Date updated

Borland Construction

2923

SE ¼ 20-9-17W

June 2 to July 15, 2014

 

Maple Leaf Construction

2831

SE 23-8-14 E

Beginning June 14, 2012

 

Nelson River Construction

2925

SW 17 - 6 - 19 WPM RM of Whitewater PTH# 10

July 15 - Aug 15, 2014

 

Nelson River Construction

2826

SW 34-17-5 WPM RM of Rosedale

May 15 - July 1, 2014

 

Mulder Construction

2822

SW 5 – 12 – 7 W Portage La Prairie PTH #1

June 2014 – Oct 2014

 

Mulder Construction

2823 R

NW 2 –11– 14 W, Carberry

May 2014 – June 2014

 

Mulder Construction

2823 R

NE 22 - 8 - 5 W Carman to Elm Creek

June 2014 – Aug 2014

 

Mulder Construction

2823 R

SW 2 - 19 - 7 EPM

In Aug 2014

 
Mulder Construction 2916 SE 34 - 13 - 19 W, Rapid City June 2014 - August 2014  
Mulder Construction 2916 NE 25 - 14 - 3 W, Woodlands (PTH #6) July 2014 - September 2014  
Mulder Construction 2916 PTH #59 from Brokenhead to PTH #11 August 2014 - October 2014  
MIT 3013 http://www.gov.mb.ca/conservation/eal/registries/index.html 2014 Construction Season  
Borland Construction 2923 SE ¼ 09-26-07 W September 1 - December 31, 2014 August 18, 2014
Nelson River Construction 2826 SW 07-41-10 W September 7 - November 15, 2014 August 27, 2014