Public Registry 1071.10

City of Winnipeg - North End Water Pollution Control Centre

Latest information was posted March 1, 2024

________________________________________________

Progress Reports

________________________________________________

2024-02-29 North End Water Pollution Control Centre - Acute Lethality Test Failure Environment Act Licence No. 2684 RRR - Clause 29 - posted March 1, 2024

2023-01-05 Notice of Alteration Approval - posted January 10, 2023

2022-12-23 Temporary Storage of Grit Screening Waste Authorization - posted January 10, 2023

2022-11-21 Notice of Alteration Approval - posted November 21, 2022

2022-10-19 Notice of Alteration Form - posted November 21, 2022

2022-10-19 Notice of Alteration - posted November 21, 2022

2022-09-09 Approval letter- Omands Creek Release Closure Report - posted September 27, 2022

2022-07-14 Omands Creek- S Lambert’s Letter and Closure Report - posted September 27, 2022

2022-06-14 Dry Weather Overflow Event Report Response - posted July 12, 2022

2022-06-24 EAB Response to City of Winnipeg (NEWPCC & SEWPCC) - posted June 30, 2022

2022-04-14 Interim Phosphorous Reduction and Upgrade Plan Update Report Acknowledgement - April 19, 2022

2022-03-11 Enhanced Interim Phosphorous Reduction Additional Information - April 19, 2022

2022-02-15 Interim Phosphorous Reduction and Upgrade Plan Update Report - April 19, 2022

2022-02-25 Enhanced Interim Phosphorous Reduction Options Assessment Letter Response - posted March 3, 2022

2021-12-29  Enhanced Interim Phosphorous Reduction Options Assessment Letter - posted March 3, 2022


Interim Phosphorous Removal and Facility Upgrade

2021-12-23 Letter to City of Winnipeg - posted December 23, 2021


Portage Avenue Interceptor Sewer Notice of Alteration

2021-12-20 Notice of Alteration Approval – Portage Avenue Interceptor Sewer - posted December 20, 2021

2021-12-15 Notice of Alteration Form - posted December 20, 2021

2021-12-15 Notice of Alteration – Portage Avenue Interceptor Sewer - posted December 20, 2021

2021-05-28 - Notice of Alteration Approval - June 1, 2021

2021-04-30 Notice of Alteration - June 1, 2021

2021-03-12 Request to Submit Notice of Alteration - June 1, 2021

2020-12-17 Interim Phosphorous Removal Detail Review and Testing Report - June 1, 2021

October 16, 2020 Interim Phosphorous Reduction Plan and Upgrade Process Requirements - posted October 16, 2021

September 30, 2020 Interim Phosphorous Reduction Plan and NEWPCC Upgrade Plan Update - posted October 9, 2020

January 31, 2020 Interim Phosphorous Reduction Plan and Nutrient Removal Implementation Plan - posted January 31, 2020

_______________________________________________

Project Advisory Committee

_______________________________________________

December 27, 2019 Progress Report - posted January 17, 2020

Environment Act Licence 2684 RRR - posted December 5, 2019

December 5, 2019 Notice of Alteration Response - posted December 5, 2019

July 30, 2019 Notice of Alteration Request to Alter Clause 13 (c) - posted December 5, 2019

January 23, 2019 Request for Notice of Alteration Submission - posted February 8, 2019

October 22, 2018 Notice of Alteration Approval - posted November 6, 2018

December 28, 2017 Notice of Alteration Request - posted January 9, 2019

December 30, 2014 Notice of Alteration approval - posted January 5, 2015

Approval of City of Winnipeg North End Water Pollution Control Centre-s Master Plan - posted July 7, 2014

City of Winnipeg North End Water Pollution Control Centre Master Plan - posted November 5, 2014
Submission Letter

Environment Act Licence 2684 RR

 

Environmental Approvals Contact: Asit Dey