New Daly Overpass on PTH 10 in Brandon

Project description

The 3-year project involves the construction of a new four-lane bridge with a separate pedestrian and active transportation bridge. The design will also include a new on and off ramps to connect 18th Street with Pacific Avenue, new pathways, sidewalk and pavement upgrades. In addition to the extensive bridge and road construction, the project requires demolition of several properties including the over a 100 year-old Kullberg’s building, as well as relocation of multiple public and municipal utilities.

Daly Overpass Project (PTH 10 - Brandon) (PDF, 2.8 MB)


Upcoming work

April 2021 - Exterior demolition of the Kullberg’s building.

May 2021 - The east end of the Homefarms building (approximately 24 meters or 80 feet in length) will be entirely demolished. The remaining portion, including Cree Nation Child and Family Caring Agency and the YWI Immigration Services, will not be demolished. These agencies will be open during demolition.

 


Photo updates

Manitoba Infrastructure will continue to provide photo updates throughout the construction period.

Demolition on the Homefarm building has started

 

Kullberg's demolition is nearing completion

 

April 15, 19 and 21, 2021 - Construction continues

 

Project Update – April 7, 2021 – Demolition started on the office portion of the Kullberg’s building. Project Update – April 7, 2021 – Demolition started on the office portion of the Kullberg’s building.
Project Update – April 7, 2021 – Demolition started on the office portion of the Kullberg’s building. Project Update – April 7, 2021 – Demolition started on the office portion of the Kullberg’s building.
April 7, 2021 - Demolition started on the office portion of the Kullberg’s building.

 

 

Project Update - February 24, 2021 – Wheat Kings signs coming down Project Update - February 24, 2021 – Wheat Kings signs coming down
Project Update - February 24, 2021 – Wheat Kings signs coming down